Your primary contact for questions or information regarding expired permits on your property is our shared email account expiredpermits@wpb.org.
How to close an old or expired permit
To start the process for closing an old or expired permit we require a signed letter. This letter must include the address, permit number, and the reason for requesting to close the permit. This letter must also answer the following question: Was the scope of work for this permit completed, or was it not completed? This letter must be signed by either the current property owner or the qualifier (license holder) of the contractor of record of the permit. This letter must be attached to an email sent to expiredpermits@wpb.org.
After staff receive your letter, your permit situation will be evaluated. Please read the five possible scenarios below so that you know which one is applicable and you can reduce the time needed to get the permit closed.
The process for closing an old or expired permit
A permit application (meaning, a permit that was never issued) will become Abandoned if 180 consecutive days (6 months) have elapsed with no activity on the part of the owner or the owner's contractor to continue the application.
An issued permit will become Expired if 180 consecutive days (6 months) have elapsed from the Issue Date without a passed or partially passed inspection.
The most important factors in evaluating your old or expired permit is 1) whether or not the scope of work was started or completed and 2) whether the permit you are trying to close was ever issued or not. If it was issued, it's now Expired. If the permit application was never issued, it's now Abandoned.
There are five possible scenarios as described below. Each request to close an expired or abandoned permit must be evaluated on a case-by-case basis and additional requirements may apply.
If the permit was issued more than six years ago and work was completed, but the permit was never closed out
Upon receiving the signed letter, we will have an inspector go to the property and confirm that they do not see any apparent safety hazard associated with the work. Once that is confirmed, per Section 553.79(16)(c), Florida Statutes, the permit will be Canceled.
If the permit was issued less than six years ago and the work was completed, but the permit was never closed out
Upon receiving the signed letter, we will require payment of a Renewal fee of $75 to renew the expired permit. Any remaining required inspections must then be scheduled and passed. The original permit documents and permit card must be printed and onsite for the remaining inspections. All permits require a passed Final inspection in order for the permit to properly close as Complete. Some permits require multiple Final inspections.
If the original contractor of record is no longer affiliated with the project, then a Change of Contractor request must be submitted to ds@wpb.org. A Change of Contractor request carries a separate $100 fee. After the new contractor has taken over the permit we will provide you with copies of the original stamped plans, as well as a revised permit card. A new notice of commencement (NOC) will need to be recorded in County Official Records. Then the required inspections must be scheduled and passed.
If the permit was issued and the work did not commence
Upon receiving the signed letter, staff will schedule a Cancelation Inspection. We will send an inspector out to the property to verify that the work did not commence. Once confirmed, the permit will be Canceled.
If the inspector determines that the work did start, then the Cancelation inspection will fail and the permit will remain open. Staff will discuss next steps with you.
If the permit application was never issued and the work was completed
Upon receiving the signed letter, staff will determine that the work was completed without the required permits and inspections. Because the original permit application is Abandoned, a new permit application will be required to be submitted in our Civic Access portal. The new permit application must go through the permit process this time and be approved and issued and the required inspections scheduled and passed, including all Final inspections, in order to close the permit as Complete. Once the new permit is closed, staff will administratively cancel the original Abandoned permit application as having been replaced by the new permit.
If the permit application was never issued and the work did not commence
Upon receiving the signed letter, staff will schedule a Cancelation Inspection on the Abandoned permit application. We will send an inspector out to the property to verify that the work did not commence. Once confirmed, the permit will be Canceled.
If the inspector determines that the work did start, then the Cancelation inspection will fail and the permit will remain open. A new permit application will be required to be submitted for the work that was completed.